Trouville Hospital

trouvilleIn June 1915, Major-General FT Clayton, when Inspector-General Communications, refused Lord Michelham’s offer of taking over the Royal Hotel, entirely at his expense, at Trouville suburb, Deauville. His offer was declined due to the remoteness and difficulty of supplying the hotel, which could accommodate 250 convalescing officers.1

Two years later, on 19 April 1917, the Quartermaster-General informed the Director of Works that it had been decided to establish hospitals in the Trouville area, to the west of Le Havre, as soon as the French authorities approved. The plan was to use available buildings in the area with the Casino at Trouville accommodating 1,000 beds and the Royal Hotel at Deauville 1,000 beds. A long way short of the 20,000 beds and 10,000 convalescent places required.2

On 7 May the QMG convened a conference at his office with senior officers, including the Adjutant General, General Officer Commanding, Engineer in Charge, the Directors of Works, Transportation and Transport and the Director-General Medical Services. He reported that the French authorities had given their approval for the Trouville site and a new hospital centre at Trouville was sanctioned, despite the difficulties highlighted in 1915. Admiralty pressure to keep more wounded in France due to the increasing danger to Hospital Ships from enemy submarines had won the day.3

An entirely new hospital camp was to be built on an area of 350 acres defined and designated ‘Trouville Hospital Centre’ on 18 July 19174.

Bizarrely, in the rural Trouville area, it was to be on Mont Canisy, a plateau, some 300ft above sea-level, about two miles south of Trouville railway station. The only access to the plateau was by three very narrow roads with an average gradient of 10%. Little more than farm tracks they were unable to withstand the lorry traffic necessary to service either the building of, or supply of the camp, requiring constant maintenance.

It was estimated that 27,000 tons of construction materials would be needed over 100 days. Thereafter, the normal hospital supplies plus 100 tons of foodstuffs would be needed for the planned 40,000 staff and patients at the camp.

A conference was convened to determine what transport would be needed. Light railway was the chosen system, provided the gradients were countered by winding the railway around the hill. Ensuring that the gradient would never exceed 2.5%, two miles of rail were required to reach the summit.

A Transhipment Station from the broad-gauge railway was built at Tourgeville Halte. Sidings were constructed to each hospital atop the plateau and the LR stretched for 5.5 miles. The rail chosen was 60cm, 20lbs per yard, flat bottom section clipped to steel sleepers.5

The cost for the rails alone amounted to £116,160 [£7,033,880 in 2024].6

Headquarters of the railway was established at Tourgeville, with a camp for sixty-five skilled personnel and repair sheds for the rolling stock. A diagrammatic board was installed in the Control Office and the movement of trains was controlled by a telephone system. This ensured that the ‘up and down’ trains safely passed at the passing loops built into the single-line track. Maximum number of trains on the line at any one time was eight.

The locomotives were 4-6-0 types, built by the American Baldwin Locomotive Works. The 4-6-0 type was chosen over the favoured 2-6-2 design simply because it was quickly available from Baldwins7.

They were capable of hauling a train up to fifty tons gross weight to the top of the plateau. There were 100 wagons available with either 3.5 or 9.5 tons capacity, and covered ambulance wagons with room for thirty patients. The maximum amount carried in one week was 3,736 tons, with the loading/unloading speed determining the tonnage carried, which never reached its potential capacity.8

Despite being the preferred transport system, it was November 1917 before the railway was fully functional. Difficulties obtaining sufficient land from the French and the difficult terrain slowing construction were the main reasons for the delay. The burden of transport naturally fell on the roads while the railway was being constructed. With forty 5-ton Foden steam lorries, often doing several journeys per day, the roads needed constant maintenance. Remarkably, during this period the roads were also widened and by November the existing single-track lanes were eighteen feet wide, enabling the lorries to easily pass each other. The nearest suitable roadstone was quarried from the Caen area and conveyed by rail to Tourgeville.8

trouvilleA Supply Depot was opened at Trouville, at the mouth of the River Touques for the sole purpose of supplying the hospitals in the area. Trouville Supply Depot was an outstation of No.1 Supply Depot, Havre. The depot later moved to the Army Ordnance Department depot in the old timber yard at Deauville Quay. By this time the feeding strength of the depot had risen to 250 and the staff consisted of one Captain, two Sergeants, three Other Ranks with labour provided entirely by Prisoners of War.

When the Deputy Director of Transport visited Trouville on 24 July, he discovered 1,600 tons of stores just lying at various locations pending transport to permanent store, or where they were needed. He ascertained that this was due to lack of labour rather than lack of transport. Stores not arriving at regular times or quantities also caused difficulties with the onward distribution of supplies.10 

The Depot moved onto Mont Canisy following the erection of permanent buildings.11

It comprised General Stores, Medical Comforts, ambient and chilled Meat Stores to hold one week’s supply. Personnel were accommodated in the Officer’s Mess, Sergeant’s Mess with kitchen, Dining Room, Cookhouse and three buildings for ninety men and thirty-three officers. Cost of the buildings was £10,608 [£642,350]. Baths, ablutions, latrines, etc. cost an additional £1,510 [£91,436].12

A bakery comprising four Perkins ovens, closed in brickwork and covered in clay was commissioned in August, negating the need for the daily packet boat from Havre.13 The bakery moved with the Supply Depot onto the Mont Canisy in March 1918, when it expanded to six ovens costing £4,127 [£249,904], including the buildings that housed it.14

On 1 June, Lt Col PJJ Radcliffe, RE was appointed CRE, Trouville,15 to work under the Director of Works, with temporary offices in Trouville. He was to oversee the scheme intended to provide three hospitals of 5,000 beds, and three convalescent camps for 5,000 men each. The hospitals would be accommodated in Nissen Hospital Huts and the camps in Nissen Bow Huts. Each convalescent camp was to include a parade ground with capacity for 4,000 men.

Contracts were awarded to Messrs George Trollope & Sons and Colls & Sons Ltd to supply the hospitals from England. This necessitated them chartering the shipping and a quay at Deauville was made available. They were also required to ship whatever extra RE stores were required but not available in France.

The Director of Works reported that he needed four Sappers per 100 beds and the War Office was asked to send three Army Troops Coys, RE complete with tools and transport to France along with two Labour Coys providing 1,000 unskilled labourers. Nos.7 and 8 AT Coys from the Royal Monmouth Royal Engineers arrived at Havre aboard ss.Hunslet on 12 June and subsequently at Trouville on 13 June.16

First to be constructed were the huts to accommodate the Royal Engineers, the seven Prisoner of War Companies, Trollope and Colls’ own skilled men and miscellaneous unskilled labourers etc. Once the construction tradesmen had been accommodated the convalescent depots were built. These were No.13, 14 and 15 Convalescent Depots with No.13 opening on August 4. No.14 Convalescent Depot opened on August 30 and 15 on October 25. Only No.13, commanded by Lt Col S Boylan Smith, RAMC, provides any meaningful detail in their war diary.17

The 5,000 bed Depots included an administration block, quartermaster’s block and a central dining hall with seating for 2,500. Unusually, the depots were fully hutted from the outset, comprising twenty groups of sixteen Nissen Bow Huts. Each hut was heated by a stove and had electric light. Each Depot had a Russian Steam Bath with shower, a Dental Institute, Eye Specialist Institute, Barber’s Shop, Chaplain’s Quarters, Drill Shed and Miniature Rifle Range. The cost of each depot, using Royal Engineers and Prisoner of War labour, supervised by the CRE, and Trollope and Sons was £40,000 [£2,422,135].18

At Nos.13 and 14 Depots, all the convalescents dined in a large hall of 100ft x 168ft in two shifts. In No.15 Depot, three dining halls were built, two for 1,000 men each and one for 500. Each had their own cookhouse. Initially the huts had wood lining, but the men soon ripped the lining from the walls to use for firewood. Corrugated iron linings replaced those used for firewood. No.15 Depot was situated in a very windy position and suffered from the wind tearing the oiled linen curtains.  

By the time, construction of the hospitals was able to begin, in November, the specification had been modified from the original 5,000 bed capacity to the more realistic 2,500 beds. Three General Hospitals were built, being Nos.72, 73 and 74. Each was separated from the others by open spaces, was self-contained and served by light railway sidings from the main LR line from Tourgeville. The railway brought walking wounded and convalescents up to the Centre as well as the necessary stores.

Each hospital had twelve blocks of Nissen Hospital Huts, ten with twenty-five bed wards with an accessory block containing a Dressing Room, Nurses Room and Scullery with accessories, Bedpan Rooms and Night latrines. There was one block of five wards and one accessory hut. A single Officer’s block with five wards in Nissen Hospital Huts, accessory Block, Lavatory, Latrines, Kit Room, Officer’s Mess, Ante-Room and kitchen.

Each hospital had its own Operation Block, Laboratory and Personnel Compound to accommodate 100 Officers and 2,400 men. The other buildings were of timber framework with painted or tarred corrugated iron walls. A central Cook House and large Dining Hall able to seat 900 patients at a sitting provided for those patients not confined to bed. Contracts with Trollope & Sons and Colls & Sons were signed on 15 June 1917, with the cost of each hospital being £234,173 [£14,179,965]. No.74 General Hospital also included an Isolation Hospital of five self-contained patients blocks, each containing four wards for two cases and two wards for one case.19

The three General Hospitals mobilised from Blackpool, Lancashire.20 No.72 on 14 November 1917, arriving Trouville on 6 December, 73 on 21 January 1918, arriving on 26 January and 74 on 25 February 1918, arriving 8 March. All three departed England from Southampton and disembarked at Le Havre.

The bombing of Etaples during the Spring of 1918 resulted in the St John Association Hospital and the Liverpool Merchants BRCS Hospital being transferred to Trouville and a new hospital was built to accommodate the 1 Canadian Hospital, also from Etaples.

trouvilleSt John Ambulance Association insisted on using their own contractors, Humphrey & Co to reassemble their ‘demountable’ huts. This proved less successful and time consuming than The Liverpool Merchant’s Hospital who used the War Office contractors, Trollope & Sons and Colls & Son Ltd who gave most satisfactory service considering the site was on a slope. The Canadian Hospital was also built by Trollope under Royal Engineer’s supervision.21

Between 4 August 1917 and 19 February 1919, No.13 Convalescent Depot admitted and discharged 66,798 convalescents with 57,600 discharged by the Armistice. Attempts to employ convalescents with helping construction and maintenance of the hospitals and depots failed as, despite only expected to work a four-hour day, they considered they had earned a rest and refused to work.22

The unit closed on 28 February 1919 and reopened on 3 March as No.4 Prisoner of War Convalescent Depot with no final closing date recorded.



1 The National Archives, WO 95/3957 – War Diary, Inspector-General Communications, 3/6/1915

2 TNA, WO 106/1484 – Trouville Hospital Centre

3 ibid

4 ibid

5 TNA, WO 106/1484 – Brief History of the Trouville Hospitals Light Railway

6 TNA, MUN 5/389 – Railway Material Licences Department. Bank of England inflation calculator.

7 David W Ronald and Roy Link, WDLR Companion, RCL Publications

8 TNA, WO 106/1484 – Brief History of the Trouville Hospitals Light Railway

9 TNA, WO 106/1484 – Trouville Hospital Centre

10 TNA, WO 95/4005 – War Diary, Deputy Director of Transport (Southern)

11 TNA, WO 158/2 – Directorate of Supplies, Trouville Supply Depot

12 TNA, WO 106/1484 – Trouville Hospital Centre

13TNA, WO 158/2 – Directorate of Supplies, Trouville Supply Depot

14 TNA, WO 106/1484 – Trouville Hospital Centre

15 CRE - Commander Royal Engineers

16 TNA, WO 95/4049 – War Diary, 8 Army Troops Coy, Royal Monmouth Royal Engineers

17 TNA, WO 95/4121 – War Diary, No.13 Convalescent Depot

18 TNA, WO 106/1484 – Trouville Hospital Centre

19 TNA 106/1484 – Trouville Hospital Centre

20 No.53 General Hospital was the first to mobilise from Blackpool on April 12th 1917. Subsequently, Nos.54,55,56,57,58,72,73,74 General Hospitals mobilised from the Sheffield Training Centre, Blackpool. No information regarding Sheffield Training Centre has been found to date

21 TNA 106/1484 – Trouville Hospital centre

22 TNA, WO 95/4121 – War Diary, No.13 Convalescent Depot

 

 

ABBREVIATIONS
CONTENTS
WAR OFFICE CODENAMES
WE CAN DO IT
SITE MAP
DESTINATION WESTERN FRONT